GREAT CANADIAN PROJECTS
The solution was to enclose the waste
and potentially contaminated materials
within a massive containment cell.
The cell, which measures 108 metres
wide by 115 metres long and ranges
between four to 10 metres below
grade was built two years ago. The
total cost of this part of the project,
which included an engineered cap
over the cell, totalled approximately
$1.5 million.
C3 Environmental Limited, an envi-ronmental
engineering and contracting
firm based in Breslau, Ont., played a key
Waste at the
surface and at
shallow depths
was removed
and disposed
of at a licenced
landfill prior to
construction of the
containment cell.
The Waterloo Barrier® system
at Randle Reef Remediation
Project in Hamilton, Ont.
role in the remediation effort, assisting
with the project design and providing a
unique solution known as the Waterloo
Barrier® System that was used to encase
the waste.
According to Minh Le, president of C3
Environmental, the containment cell was