however, the unique challenges created by the tight quarters  
 of the site in busy downtown Toronto required both to  
 be constructed simultaneously. Furthermore, the owners of  
 the Massey Tower project donated a strip of land to Massey  
 Hall as a necessity in order to enable both the Massey Hall  
 Revitalization and the new Massey Tower construction to  
 take place. Neither project would have been possible without  
 the other. 
 Neighboring the property to the north is the former Bank  
 of  Toronto  building  (built  circa  1905)  and  to  the  south  is  
 Heintzman Hall, which was occupied by the famous piano  
 company,  “Heintzman  &  Company,”  from  1912  to  1971.  
 Additionally, to the southeast of the property is the Elgin &  
 Winter Garden Theatre (EWG) which was built in 1913 and  
 is a landmark of its own in the Toronto theatre community. 
 The close proximity of existing foundations and walls of  
 these heritage buildings (each over 100 years old) – and the  
 need to protect them – were a complicating factor for the  
 foundation and shoring work of both projects. The new structures  
 required foundations to be installed deeper than and  
 very close to the footings of the adjacent heritage buildings.  
 Due to the sensitivity of these old footings, the shoring and  
 caisson drilling had to be completed from several different  
 benched elevations using different equipment and techniques  
 to suit the needs of each phase of the foundation work. 
 The project’s shoring and caisson foundation works were  
 undertaken and executed under a carefully planned construction  
 sequence by  Deep  Foundations  Contractors  Inc.  
 (deep). deep overcame unique challenges and provided solid  
 foundation solutions for both projects to rise as successors in  
 the Massey Hall legacy. 
 The foundation works 
 To effectively excavate for both projects, a single shoring  
 system connecting  the  two properties  had to  be  designed.  
 deep’s work  for  the projects  included a secant wall  shoring  
 system, braced with soil and rock anchors, for four levels of  
 underground facilities for Massey Tower and two levels for  
 Massey Hall. The excavation for Massey Tower was founded  
 in sound bedrock. The Massey Hall excavation, on the other  
 hand, did not extend as deep, so caissons and structural piles  
 were  required to  support  the new structure’s loads. Massey  
 Hall’s foundation design consisted of a combination of 28  
 structural shoring piles and 29 caissons, which were used to  
 help carry the loads for the new structure to bedrock. 
 Maximizing real estate meant shoring walls were exceptionally  
 close to the existing buildings. Eighty per cent of the  
 piles on the project had to be drilled with the mast of the drill  
 rig within inches of historic buildings. Crew and operators  
 had to be constantly vigilant to ensure that equipment did  
 not make contact with any of the structures or that the drilling  
 and vibrations did not cause cave-ins or compromise any  
 of the existing foundations. 
 Each of the buildings immediately surrounding the project  
 had to have their footings exposed and located. Once the  
 footing locations were verified, the shoring design and drilling  
 methods were determined to match the field conditions.  
 In many cases, the edge of the drilled hole had to be inches  
 PROJECT SPOTLIGHT 
 Rendering of Massey Hall Revitalization 
 50 Q2  2017  www.pilingcanada.ca 
 
				
/www.pilingcanada.ca
		/www.pilingcanada.ca